Earned vs burned for construction
What the job has earned, next to what it has burned.
Appello's Earned vs Burned report puts each cost code's earned value, from the percent complete your PM approved, beside the actual cost of labour, bills and equipment. CPI, a forecast at completion and a status on every line follow. It is for owners, controllers and PMs at ICI trade contractors, and it is live today.
Earned vs Burned Report
As of 2026-08-31Group by: Cost CodeBudget (BAC)
$320,000
Earned (EV)
$229,600
Actual (AC)
$227,500
CPI
1.009
EAC
$317,073
VAC
$2,927
Earned Value Trend
Performance Insights
Cost Performance
CPI of 1.009 indicates that the project is performing under budget.
Forecast at Completion
Project is forecasted to complete under budget by $2,926.83.
Job › Financials & Reporting › Earned vs Burned, for 26-014-01 Lakeshore General · Wing B. Fictional sample company and data.
Spent is not the same as done
A job cost report says jacketing has used 62% of its budget. That sounds fine until someone asks how much of the jacketing is finished. Earned vs burned answers the second question with the first number beside it.
Without it
- Budget used, with no idea of progress.
- The overrun shows up when the money runs out.
- “How's jacketing going?” gets a shrug.
With it
- Earned and actual on the same line.
- At risk the month it starts slipping.
- “Jacketing earned $27,000 for $33,700.”
The 10% line
Every line on the report gets a status. It is at risk when it has cost more than it has earned, and over budget when that gap passes 10% of the line's budget. Earned depends on the percent complete your PM approves, so move it and watch what happens to jacketing on Wing B.
410 - Jacketing
Over Budget- Budget (BAC)
- $54,000
- Actual (AC)
- $33,700
- Earned (EV)
- $27,000
- CPI
- 0.801
Cost variance (EV − AC)
−$6,700
At 50%, jacketing has earned $27,000 for $33,700 spent: over budget. If the foreman is right that it is closer to 55%, it is still behind, but only at risk. From 63% up it is on budget. The approved percent is a judgement, so Appello shows you exactly what that judgement does to the line.
The job looks fine. Read the lines.
Wing B is $2,100 ahead overall, because pipe insulation is well ahead. Underneath, two scopes are behind. That is the pattern earned vs burned exists to catch.
| Cost code | Budget | Approved % | Earned | Actual | CV | Status |
|---|---|---|---|---|---|---|
| 210 - Pipe insulation | $148,000 | 85% | $125,800 | $113,400 | $12,400 | On Budget |
| 320 - Duct wrap | $96,000 | 80% | $76,800 | $80,400 | −$3,600 | At Risk |
| 410 - Jacketing | $54,000 | 50% | $27,000 | $33,700 | −$6,700 | Over Budget |
| 510 - Firestopping | $22,000 | 0% | $0 | $0 | $0 | Not started |
As of Aug 31, 2026. Firestopping has no progress or cost yet. Fictional sample company and data.
Nine numbers, worked out for you
Earned value management has a reputation for being an accountant's tool. On the report, each one carries an info dot. Here is what each one means, with Wing B's value as of August 31.
- BAC$320,000
Budget at completion
The line's budget
What the four costing codes were budgeted to cost.
- EV$229,600
Earned value
Approved % × budget
The budget the finished work has earned so far.
- AC$227,500
Actual cost
Labour + bills + equipment
What has actually been approved against the job.
- CV$2,100
Cost variance
EV − AC
Positive: the work cost less than it earned.
- CPI1.009
Cost performance index
EV ÷ AC
Above 1, every dollar spent earned a little more than a dollar.
- EAC$317,073
Estimate at completion
AC + (BAC − EV) ÷ CPI
Where the job lands if it keeps performing this way.
- ETC$89,573
Estimate to complete
EAC − AC
What the formula says is left to spend.
- VAC$2,927
Variance at completion
BAC − EAC
Under budget at the finish, if nothing changes.
- TCPI0.977
To-complete performance index
(BAC − EV) ÷ (BAC − AC)
The efficiency the rest of the job needs to hit budget.
Rounded for display. The report also shows SPI. Fictional sample company and data.
Read the same job seven ways
Group the report by cost code, or by the spec labels on each code: area and system, area, system, phase, module or component. Pick an as-of date to see the job as it stood at any progress report. The cost breakdown chart splits actual cost into labour, equipment and materials, and the whole report exports to CSV.
How spec labels work →Which report answers which question
Job cost report
“How much has this job cost, line by line, against budget?”
Budget vs actual, the financial summary and the monthly cost report.
Earned vs burned
“Is the money we've spent buying the progress we expected?”
Earned value against actual cost, CPI and a status on each line.
WIP report
“Across every job, are we over or under billed today?”
Contract, cost to date, cost to complete and over or under billing, as of any date.
Ask which line is slipping
Appello works natively with Claude, ChatGPT, Microsoft Copilot and Grok through the Appello connector (MCP). The assistant reads the same report with the same formulas, limited to the jobs your Appello role lets you see. Sample answers use the fictional jobs.
Are we burning more than we're earning on Wing B?
Not overall: $229,600 earned for $227,500 spent, CPI 1.009. But 410 Jacketing is over budget and 320 Duct wrap is at risk.
Appello tool: get_earned_vs_burned
Which cost codes across my open jobs are over budget?
A list by job and code, worst first, with earned, actual and the gap, limited to the jobs your role lets you see.
Appello tool: get_earned_vs_burned
Has jacketing's CPI been getting better or worse since June?
The assistant reads the report as of each progress report date and lists the line's earned value, actual and CPI side by side.
Appello tool: get_earned_vs_burned · get_cost_to_complete
Agent playbook · Month-end costing
After the month's progress reports are approved, an agent reads earned vs burned on every open job, lists lines that turned at risk or over budget since last month, and drafts a note for each PM with the hours and bills behind them. The PM decides what to do about it.
timesheets approved in Appello
Across all customer accounts, counted 2 September 2026
Actual cost you can trust starts with the timesheet
Earned vs burned is only as good as the actual cost on each line. In Appello, that cost comes from approved timesheets, coded bills and equipment time, not a monthly import, so the report is current the day the week is approved.
Questions about earned vs burned
Is earned vs burned measured in hours or dollars?
Dollars. In Appello, earned is the approved percent complete times the line's budget, and burned is the actual cost on that line: approved labour, approved bills and expenses, and equipment time. Labour is costed at the rate each worker was paid, so a crew of apprentices and a crew of foremen are measured fairly.
Where does percent complete come from?
From the job's progress reports. In Appello, the project manager approves a cumulative percent for each line on each report, and that approved percent drives earned value. The same report drives the progress invoice, so the job is never 80% complete for billing and 60% complete for costing.
What does at risk or over budget mean?
In Appello, a line is at risk when it has cost more than it has earned, and over budget when that gap is more than 10% of the line's budget. Lines with no budget are marked so you can fix them. The status sits on every row, so the line that needs a conversation is easy to find.
Does it need a schedule of values?
Yes. In Appello, the Earned vs Burned tab reads the job's cost codes and the percent complete approved against them, so the job needs its lines set up first. Generate them from the won estimate or apply a template, approve the first progress report, and the report fills in.
Can I export it for my accountant or bank?
Yes. In Appello, the report exports to CSV. Most controllers send the WIP report outside the business and keep earned vs burned for the project review, because it explains why a job's margin is moving.
Is EAC the same as the PM's forecast?
No. In Appello, EAC on this report is a formula: actual cost plus the remaining budget divided by CPI. The project manager's forecast lives on the Cost to Complete tab and is the number the WIP report reads. When the two disagree, that is worth a conversation.
Before and after earned vs burned
Before
Progress reports →
The approved percent that earned value is built on.
Before
Cost codes →
The lines cost lands on, from one template.
After
Cost to complete →
Turn what you learned into the PM's forecast.
After
WIP report →
The forecast reaches every job's over or under billing.
Part of construction job costing software for insulation, mechanical, HVAC, plumbing, sheet metal, electrical, concrete and other ICI trade contractors.
See your jobs earned vs burned
Bring a job that worries you. We'll set up its cost codes, approve a progress report and show you which lines are slipping.
See your job's margin in a demoA working session on your own week: your crews, your payroll rules, your jobs. Pricing for your team size afterwards.
- I want a quick benchmarkScore your operationSix minutes, five scored areas, and a report you keep, whether or not you ever book a demo.
- I'm researching AIRead the AI agents white paperAI Agents in Construction: what agents can do for a trade contractor today, what has to be in place first, and the practical next steps.
- I want the big pictureSee how Appello connects AIHow your operations data, your integrations and assistants like Claude and ChatGPT fit together.